Project Details
  • Bear Run Phase V
    No
    Underground
    Active Treatment System
    Susquehanna
    Bear Run

    At the Bear Run Phase V, a Swedish-Bucket Lime Silo was installed to treat a discharge exiting the Bank #2 Drift Mine. To decrease the cost, an older lime silo was purchased from Consol Energy and retrofitted with the Swedish-Bucket dumping system.

Water Quality Data Summary
Sample PointFlow - Field!!(gal/min)pH - Field!!(S.U.)pH - Lab!!(S.U.)ORP - Field!!(mvolts)DO - Field!!(mg/L)Temp - Field!!(C)Cond - Lab!!(umhos/cm)Alkalinity - Field!!(mg/L)Alkalinity - Lab!!(mg/L)Acidity - Lab!!(mg/L)T. Fe  - Lab!!(mg/L)D. Fe - Lab!!(mg/L)T. Mn  - Lab!!(mg/L)D. Mn  - Lab!!(mg/L)T. Al - Lab!!(mg/L)D. Al - Lab!!(mg/L)SO4 - Lab!!(mg/L)TSS - Lab!!(mg/L)
5.1582.953.07----10.6823001503.38--1.34--14.94--3013.5
5.218.45.194.97----18.7657010.3346.332.04--0.85--7.3--251.34
Treatment Technologies
Treatment Technology Quantity of Elements
Chemical Doser 1