Martin's Run Diversion Well

Martin's Run Diversion Well

Project Details
Original Construction Year 1997
Most Recent Rebuild Year
Total Cost 0.00
Total Capital Cost $5,000.00
Latitude / Longitude Method Unknown
Latitude 40.658600
Longitude -76.346400
Elevation 0
Project Martin's Run Diversion Well
Project Type Passive Treatment System
Project Status
AMD Source Underground
Stream Swatara Creek
Watershed
River Basin Susquehanna
Quad Tremont
City/Township Newtown / Reilly
County Schuylkill
State PA

Description: A limestone diversion well had been installed along Martins Run near Rt 125 in July 1996 in order to treat the stream. The stream was primarily made up of the Eureka Tunnel and Colket Tunnel mine discharges. The Army National Guard (Red Horse Division provided the excavator and manpower. The well was 6 foot diameter, 6 feet deep. Approximately 160 feet of 8 inch pipe was used and provided 10 feet of vertical drop. The Frailey Township roadmaster maintained the well. In the summer of 2006 a large flood filled the diversion well with debris and possibly caused additional damage. The diversion well was removed that same summer and was not replaced.

Water Quality Data Summary

Treatment Technologies
Treatment Technology Quantity Status
Limestone Diversion Well 1 N/A
Location Links
Map
GPS Directions
Project Contacts
Contact Person:
Contact Organization: US Geologic Service (USGS)
Project Designer:
Project Designer Organization:
Project Responsible Organization: Schuylkill County Conservation District
Funding
Title Source Amount Date
EPA Section 319 EPA Section 319 $5,000.00
Organizations
no data available
External System IDs
Title System
D1-184 Datashed 1.0
PA-137 OSM
Project Performance