Project Details
  • Bog
    No
    Underground
    Passive Treatment System
    Mill Creek
    Corsica

    Sometime before May 2012, the Bog system was modified. A baffle curtain was added to the wetland and flow restrictors were added to 4 of the SAPS discharge pipes.

    2000
    $76,380.00
    $100,000.00
Water Quality Data Summary
Sample PointFlow - Field!!(gal/min)pH - Field!!(S.U.)pH - Lab!!(S.U.)ORP - Field!!(mvolts)DO - Field!!(mg/L)Temp - Field!!(C)Cond - Lab!!(umhos/cm)Alkalinity - Field!!(mg/L)Alkalinity - Lab!!(mg/L)Acidity - Lab!!(mg/L)T. Fe  - Lab!!(mg/L)D. Fe - Lab!!(mg/L)T. Mn  - Lab!!(mg/L)D. Mn  - Lab!!(mg/L)T. Al - Lab!!(mg/L)D. Al - Lab!!(mg/L)SO4 - Lab!!(mg/L)TSS - Lab!!(mg/L)
BO-Sap1right86.426.68----14.31368122.67116.67-39.1814.76--33.45--0.14--667.54
BO-Sap1left8.26.316.55----14.41241130.67122.43-25.8614.48--30.93--0.33--820.55.8
BO-Sap2right3.86.587.13----15.21349111104.67-75.472.66--2.69--0.01--707.14.3
BO-Sap2left96.376.88----15.61370132116.98-72.217.21--19.22--0.17--711.58
Treatment Technologies
Treatment Technology Quantity of Elements
Settling Pond 2
Vertical Flow Pond (VFP) 2