Skip to main content

Long Valley Run

Long Valley Run

Project Details
Original Construction Year 1997
Most Recent Rebuild Year
Total Cost 0.00
Total Capital Cost $0.00
Latitude / Longitude Method Unknown
Latitude 41.658200
Longitude -76.596100
Elevation 0
Project Long Valley Run
Project Type Passive Treatment System
Project Status
AMD Source Underground
Stream Schrader Creek
Watershed
River Basin Susquehanna
Quad Powell
City/Township Franklin Twp
County Bradford
State PA

Description: This is one of two passive systems that were originally listed under the Falls Creek - Schrader Creek system (OSM ID 76). Costs could not be separated so they are covered under the Falls Creek project. Schrader Creek - AMD 08(3295)101.1 - Bradford County: Submitted by Schrader Creek Watershed Association. Construction was completed by Maude Mining in October, 1997. The project involved the construction of two vertical flow wetland systems to treat two deep mine discharges. An extensive aquatic survey of Schrader Creek was completed by BAMR employees and PAFBC in July, 1997, to document conditions just prior to treatment. This project is expected to return seven miles of Schrader Creek to a reproducing trout fishery comparable to upstream conditions. The first samples of treated water were collected in December, by the Watershed Association. The pH has gone from the 3 - 4 to 6+, acidity have gone from 100+ mg/l net acid to 90+ mg/l net alkaline, and already low iron levels have been reduced slightly to 1.5 mg/l and less. Elevated aluminum levels have dropped to below detection in the smaller system that has been operating since September. However, aluminum levels have only been reduced by half, to 6.8 mg/l in the larger system.

Water Quality Data Summary

Treatment Technologies
Treatment Technology Quantity Status
Aerobic Wetland 2 N/A
Anoxic Limestone Drain (ALD) 2 N/A
Settling Pond 3 N/A
Location Links
Map
GPS Directions
Project Contacts
Contact Person:
Contact Organization: Schrader Creek Watershed Association
Project Designer: Charles Cooper
Project Designer Organization:
Project Responsible Organization: Schrader Creek Watershed Association
Funding
Title Source Amount Date
10% AMD Set Aside Funds AMD Set Aside Funds $632,880.00
Bond Forfeiture Bond Forfeiture $60,000.00
External System IDs
Title System
D1-329 Datashed 1.0
PA-107 OSM
Project Performance