  • Upper Latrobe Mine Drainage Treatment Project
    No
    Underground
    Passive Treatment System
    Loyalhanna Creek
    Latrobe
    Loyalhanna Creek

    This project at one time was known as the Latrobe Foundation Project. The project has been designed and built in phases and funded through several grants. The project began in 2004 with a Growing Greener grant to conduct a hydrogeologic study of the discharges completed by L. Robert Kimball Associates. Additional funding from the Growing Greener program and the US Office of Surface Mining led to the drilling of boreholes and a settling pond completed in 2005. Another Growing Greener grant was obtained in 2007 to construct a full-scale passive systems that was designed by Hedin Environmental with construction completed in June 2010.

    2005
    $172,140.00
    $160,740.00
Water Quality Data Summary
Sample PointFlow - Field!!(gal/min)pH - Field!!(S.U.)pH - Lab!!(S.U.)ORP - Field!!(mvolts)DO - Field!!(mg/L)Temp - Field!!(C)Cond - Lab!!(umhos/cm)Alkalinity - Field!!(mg/L)Alkalinity - Lab!!(mg/L)Acidity - Lab!!(mg/L)T. Fe  - Lab!!(mg/L)D. Fe - Lab!!(mg/L)T. Mn  - Lab!!(mg/L)D. Mn  - Lab!!(mg/L)T. Al - Lab!!(mg/L)D. Al - Lab!!(mg/L)SO4 - Lab!!(mg/L)TSS - Lab!!(mg/L)
LFPPIN032.856.49--1.27------144.13-68.7237.96--3.04--0.5--389.820.4
LFPPOUT3106.847.15--4.06------91.72-65.44.61--2.48--0.5--406.614
Treatment Technologies
Treatment Technology Quantity of Elements
Settling Pond 1